Sears 830 Planning Schedule
Sears · X12 004010
The Sears 830 is the planning schedule a customer sends to forecast the quantities it expects to order.
Sears’ published 830 specification, rendered as an interactive guide. Expand any segment to see its elements, data types, lengths and accepted codes — then validate your own document against it below.
Specification
12 of 12 segments
HEADING
ST
Transaction Set Header ST
pos 010
Optional
max —
BFR
Beginning Segment For Planning Schedule BFR
pos 020
Required
max —
REF
Department Numbervariant 1 of 2
Two iterations of the REF segment are required; one to specify the vendor number and a second to specify the department number.
The vendor number that will be specified in REF02 (when REF01 contains code IA) must be agreed to by Sears before testing can begin.
pos 050
Required
max —
REF
Internal Vendor Numbervariant 2 of 2
Two iterations of the REF segment are required; one to specify the vendor number and a second to specify the department number.
The vendor number that will be specified in REF02 (when REF01 contains code IA) must be agreed to by Sears before testing can begin.
pos 050
Required
max 1
N1 Looprepeats 200required
N1
Name N1
pos 230
Required
max —
DETAIL
LIN Looprequired
LIN
Item Identification LIN
pos 010
Required
max —
UIT
Unit Detail UIT
The unit of measure for all forecast quantities is each.
pos 020
Required
max —
PID
Product Item Description PID
As predetermined between trading partners, PID05 will provide a forecast ranking for the item/SKU and location referenced in the associated LIN and N1 segments. This ranking is tied to the item/SKU and location, not the forecast quantities for the item/SKU.
The number in the first position (PID05) identifies the ranking (e.g., future forecast, forecast error using standard deviation, etc.) and the alpha character in the second position indicates the inventory stratification for that ranking.
pos 080
Optional
max 1000
N1 Looprepeats 200required
N1
Name N1
pos 320
Required
max —
FST Looprequired
FST
Forecast Schedule FST
The forecast start date is the Sunday run date. The forecast end date is required for 830 transactions sent to Sears.
The Forecast Quantity Qualifier code in FST02 represents a DRP Order Planning Type within Sears’ DRP application. Some codes are used in transactions Sears receives (inbound) and some codes are used in transactions Sears sends (outbound). E.g., code A (Immediate) may be used on inbound transactions to Sears. Code A is equivalent to the DRP Order Planning Type 3 (quantity available to ship).
pos 410
Required
max —
SUMMARY
CTT
Transaction Totals CTT
pos 010
Optional
max —
SE
Transaction Set Trailer SE
pos 020
Optional
max —
Validate your 830
Paste or upload a document and check it against Sears’ published rules — segment order and repetition, required elements, field lengths, data types and accepted codes. Nothing is stored.
Go live on Sears’ 830 in days, not months
Connect this guide to your accounting system and test with Sears yourself, or leave the mapping and the test cycle to us, at no extra charge.