CVS 830 Planning Schedule with Release Capability
CVS · X12 004010
The CVS 830 is the planning schedule a customer sends to forecast the quantities it expects to order.
CVS’s published 830 specification, rendered as an interactive guide. Expand any segment to see its elements, data types, lengths and accepted codes — then validate your own document against it below.
Specification
10 of 10 segments
HEADING
ST
Transaction Set Header ST
pos 010
Optional
max —
BFR
Beginning Segment For Planning Schedule BFR
pos 020
Required
max —
REF
Reference Identification REF
pos 050
Optional
max 12
N1 Loop
N1
Name N1
pos 230
Required
max —
DETAIL
LIN Looprequired
LIN
Item Identification LIN
pos 010
Required
max —
UIT
Unit Detail UIT
pos 020
Optional
max —
FST Loop
FST
Forecast Schedule FST
pos 410
Required
max —
SDQ
Destination Quantity SDQ
pos 420
Optional
max 50
SUMMARY
CTT
Transaction Totals CTT
pos 010
Optional
max —
SE
Transaction Set Trailer SE
pos 020
Optional
max —
Validate your 830
Paste or upload a document and check it against CVS’s published rules — segment order and repetition, required elements, field lengths, data types and accepted codes. Nothing is stored.
Go live on CVS’s 830 in days, not months
Connect this guide to your accounting system and test with CVS yourself, or leave the mapping and the test cycle to us, at no extra charge.